RICHMOND, Va. (AP) - Virginia highway officials say the restoration of 11 bridges on Interstate 95 in the Richmond area was completed three months early and $16 million under budget.

The Richmond Times-Dispatch reports that a major reason for the efficient completion of the project was the off-site construction of concrete components. Virginia Department of Transportation spokesman Lindsey LeGrand says the sections were cast in a work yard in Hanover County and moved into place like puzzle pieces. The biggest piece of the puzzle was a bridge in Richmond that required 88 pre-cast bridge sections.

The project, which began in September 2010 and ended up costing $90 million, covered a seven-mile stretch of I-95 in Richmond and Henrico County that handles nearly 160,000 vehicles a day.


The comments sections of Newsplex.com are designed for thoughtful, intelligent conversation and debate. We want to hear from our viewers, but we ask that you follow our rules for commenting. E-mail is required to comment on a story, but it will not be displayed with your comment. For complete rules, CLICK HERE. The Newsplex reserves the right to not post or to remove any comment.
powered by Disqus
The Charlottesville Newsplex 999 2nd Street S.E. Charlottesville, VA 22902 434.242.1919 – Main 434.220.7522 - Newsroom
Gray Television, Inc. - Copyright © 2002-2014 - Designed by Gray Digital Media - Powered by Clickability 265047801 - newsplex.com/a?a=265047801